Buena Vista Creek Bridges on 95th and 100th Streets
THE PROJECT IS COMPLETE
Project Progression
Week 1 - Pictures from 6/7/2022
95th Street
Pictures from 6/10/2022 - Should be able to pour concrete next week
Week 2 - 6/14/22
Pouring concrete has begun
Buena Vista Creek at 95th Street
Week 3 - 6/21/22
Much of the work took place out of sight of the camera this week.
Concrete will be poured on the south side of the bridge starting on Wednesday.
Week 3 - 6/26/22
A lot of concrete was poured this week.
Week 4 - 6/29 & 6/30
Dry run and post pour
Week 4 - 7/2/22
You can now see under the bridge on 95th Street..
Week 5 - 7/8/22
Looking north on 95th Street, road surface prep heading south towards Buena Vista Creek , and the new rails.
Week 6 - 7/14/22
95th Street is now open.
Paving will take place when 100th is paved. The bridge over 100th closed today.
End of Week 6 - 7/17/22
Getting started on 100th
End of Week 7 - 7/23/2022
100th Street
Pavement and old culverts removed.
End of Week 8 - 7/30/22
Concrete pouring has started on 100th Street
End of Week 9 - 8/6/2022
Cross beams added on 100th Street
End of Week 10 - 8/13/2022
Gloomy day with pavement under plastic.
Week 11 - 8/18/2022
Shortly after sunrise.
Grating is planned for today. Then the paving the approaches to the two new bridges can begin.
Week 12 - 8/23/2022
Paving on 95th Street is taking place
End of Week 12 - 8/27/2022
Open Bridge on 100th Street